ENGINEERING (TRIBAL WELFARE)

GENERAL ABSTRACT

S.No.

Name of the Scheme / Component

Works Sanctioned

Expenditure up to March 2023

Expenditure incurred
2023-24

Cumulative Expenditure
(5+8)

Physical stage

Remarks

 

Up to last month

During the month

Total (6+7)

Completed works

Progress

Not Started

Nos.

Amount

Tender Stage

Agt.
Concluded

Site problem

Others / Not started

1

2

3

4

5

6

7

8

9

10

11

12

13

14

15

16

 

1

Buildings

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

a.

Residential School Complexes

12

5520.00

1941.47

0.00

0.00

0.00

1941.47

6

0

5

1

0

0

 

 

b.

Post Matric Hostels

13

2300.00

1691.33

0.00

0.00

0.00

1691.33

13

0

0

0

0

0

 

 

c.

Youth Training Centers

1

465.00

321.84

0.00

0.00

0.00

321.84

1

0

0

0

0

0

 

 

d.

Working Womens Hostels

1

275.00

140.27

0.00

0.00

0.00

140.27

1

0

0

0

0

0

 

 

e.

Girijan Bhavan

7

760.00

397.51

0.00

0.00

0.00

397.51

5

1

1

0

0

0

 

 

f.

School of Excellence

1

2000.00

0.00

0.00

0.00

0.00

0.00

0

1

0

0

0

0

 

 

g.

GP Buildings

199

3980.00

0.00

0.00

0.00

0.00

0.00

0

131

0

0

34

34

1-Executed by PR dept

 

 

Total :

234

15300.00

4492.42

0.00

0.00

0.00

4492.42

26

133

6

1

34

34

 

 

2

Roads (3 ITDA Infra – 2016-17)

119

9825.70

6117.41

0.00

0.00

0.00

6117.41

114

1

0

0

0

4

 

 

3

Roads (Plain areas- 2018-19)

65

11189.00

7883.23

0.00

0.00

0.00

7883.23

60

3

0

0

0

2

 

 

4

Infrastructure in 11 districts of 3 ITDAs 2022-23

121

17849.00

0.00

0.00

0.00

0.00

0.00

13

45

41

17

0

5

2-Not started
1-Completedby PR
1-Double Snction
1-Insufficient funds

 

5

N H M

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

a.

Rs.20.00 lakhs

21

420.00

385.70

0.00

0.00

0.00

385.70

21

0

0

0

0

0

 

 

b.

Rs.14.00 lakhs

97

1358.00

1257.77

0.00

0.00

0.00

1257.77

95

1

0

0

0

1

 

 

c.

Rs.16.00 lakhs

67

1360.00

897.61

0.00

0.00

0.00

897.61

61

5

0

0

0

1

 

 

 

Total :

185

3138.00

2541.08

0.00

0.00

0.00

2541.08

177

6

0

0

0

2

 

 

6

Article 275 – 2015-16 Old Spill over

19

415.70

318.67

0.00

0.00

0.00

318.67

19

0

0

0

0

0

 

 

7

Article 275 (i)

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

a.

DR Depots

17

170.00

147.46

0.00

0.00

0.00

147.46

17

0

0

0

0

0

 

 

b.

GP Model Schools

23

92.00

85.61

0.00

0.00

0.00

85.61

23

0

0

0

0

0

 

 

c.

GP Model Schools New 2020-21

15

60.00

59.26

0.00

0.00

0.00

59.26

15

0

0

0

0

0

 

 

d.

RO Plants

60

106.14

104.68

0.00

0.00

0.00

104.68

60

0

0

0

0

0

 

 

e.

Pre-Fabricated Toilets And Bathrooms Cubicles

30

219.80

152.40

0.00

0.00

0.00

152.40

30

0

0

0

0

0

 

 

f.

Addl. Infrastructure facilities

5

165.00

109.32

0.00

0.00

0.00

109.32

5

0

0

0

0

0

 

 

g.

EMRS

2

2400.00

1982.09

0.00

0.00

0.00

1982.09

2

0

0

0

0

0

 

 

h.

C/o Dormitories (Article 275(i) MOTA )

2

100.00

69.66

0.00

0.00

0.00

69.66

2

0

0

0

0

0

 

 

i.

Additional amenities – Article 275(i) 2019-20

3

125.00

57.00

0.00

0.00

0.00

57.00

3

0

0

0

0

0

 

 

j.

Subcenter buildings & Residential quarter PHC (2021-22)

8

162.00

60.72

0.00

0.00

0.00

60.72

6

2

0

0

0

0

 

 

k.

Compound walls (2021-22)

7

30.76

20.94

0.00

0.00

0.00

20.94

6

1

0

0

0

0

 

 

l.

Dormitories  to RJC’s

2

540.00

0.00

0.00

0.00

0.00

0.00

0

1

0

1

0

0

 

 

 

 

174

4170.70

2849.14

0.00

0.00

0.00

2849.14

169

4

0

1

0

0

 

 

8

SCA TO TSS

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

a.

Addl. Infra. – (2017-18)

3

270.00

141.00

0.00

0.00

0.00

141.00

3

0

0

0

0

0

 

 

b.

Compound walls (2018-19)

28

392.30

176.47

0.00

0.00

0.00

176.47

25

0

0

0

0

3

3 works cancelled

 

c.

Saving Compound walls

10

137.80

53.00

0.00

0.00

0.00

53.00

10

0

0

0

0

0

 

 

d.

Modification of existing  Toilets (2018-19)

22

214.55

165.92

0.00

0.00

0.00

165.92

22

0

0

0

0

0

 

 

e.

C/o Model Sports School

2

92.00

18.79

0.00

0.00

0.00

18.79

2

0

0

0

0

0

 

 

f.

C/o Cemonc Centers

11

113.30

55.69

0.00

0.00

0.00

55.69

11

0

0

0

0

0

 

 

g

SCA to TSS (Addl. Accommodation)  (2021-22)

2

139.18

63.47

0.00

0.00

0.00

63.47

2

0

0

 

0

0

 

 

 

Total :

78

1359.13

674.34

0.00

0.00

0.00

674.34

75

0

0

0

0

3

 

 

9

Tricor-2018-19 Maintenance & Repairs – Educational Institutions

103

516.58

443.31

0.00

0.00

0.00

443.31

103

0

0

0

0

0

 

 

10

Gurukulam Repairs

80

1089.45

878.22

0.00

0.00

0.00

878.22

80

0

0

0

0

0

 

 

11

Gurukulam Bell mouth

6

43.05

38.73

0.00

0.00

0.00

38.73

6

0

0

0

0

0

 

 

12

Ground leveling -2018-19

49

142.80

126.54

0.00

0.00

0.00

126.54

49

0

0

0

0

0

 

 

13

E.I (Spill over works) 

54

2221.00

1442.99

0.00

0.00

0.00

1442.99

52

0

0

0

0

2

2-Alternate sanction given

 

14

TRICOR 18-19 Saving amount grant works

77

119.27

70.46

0.00

0.00

0.00

70.46

76

0

0

0

0

1

 

 

15

Assistance to ITDA 

162

919.00

459.13

0.00

0.00

0.00

459.13

144

5

0

0

0

13

 

 

16

Bell mouth Gates to TW Ashram Schools and Hostels

82

307.40

80.00

0.00

0.00

0.00

80.00

59

22

0

0

0

1

1-Not Taken up

 

17

Minor Repairs

47

137.45

40.00

0.00

0.00

0.00

40.00

35

4

0

0

0

8

7-Estimate to be submitted for Major repairs

 

18

Major and Minor Repairs to TW Institutions 2022-23

59

713.71

0.00

0.00

0.00

0.00

0.00

0

59

0

0

0

0

 

 

 

Grand Total :

1714

69456.94

28455.67

0.00

0.00

0.00

28455.67

1257

282

47

19

34

75

 

 
Scroll to Top